Hydro Dam, Part 5: First Run!


Posted on November 24, 2026 by admin

Finally, the big day came… It was time to turn on the facility for real. September 28th, 2025. Pretty scary….

Well, anyways, let’s get to it. Unfortunately, I forgot to take a lot of pictures here, so you will have to be satisfied with more text than usual.

The first step was to open the valve just a bit while measuring the voltage on the induction motor to see if the turbine was spinning at all. How can we verify that the turbine is spinning? Apparently, there is a tiny bit of residual magnetism in an induction motor rotor. This means that, even with no magnets and no grid connected, the motor will produce a very tiny amount of back-EMF, which can be measured with a scope. To my surprise, this technique worked great, and we were able to verify that the turbine was, indeed, spinning. Here is a scope shot of the back-EMF with the valve opened ~20%, which is about 18Hz:

The next step was verifying that the power-up sequence was working as intended. I connected everything as it was intended, except for the main contactor which I left disconnected. This ensured that it could not close. I flipped the ‘run’ switch and ensured that the valve began to open. I flipped the main switch back to ‘stop’ and verified that the valve closed. I did this several times while monitoring the turbine electrical frequency. I allowed the valve to open to 20%, then close, 30% then close, 40% then close, etc. Everything seemed to work as intended, and experimentally, it seemed that 45% valve opening led to roughly 60 Hz turbine speed. So, I coded the board to close the contactor when the valve reached 45%.

Anyways, that was easy. Next up, the scary part- actually generating power by closing the main contactor. You can do all the testing in the world, but at some point, the contactor has to close, allowing the unstoppable force (the grid) to meet your very movable object (the turbine). I connected the 120V contactor power to my board, and prayed to the electrical gods.

Anyways, more or less, it worked.

The water began to flow:

The holes in the turbine taper began to spray:

The valve continued to open, and with a loud CLUNK, the contactor closed. A clunk is good, a BANG is bad. But a clunk it was, and we began to generate power!

However, something was off. My board reported a generated power of only 12kW, about five times less than expected. Hm, whats up?

After being sad for a little while, it finally occurred to us to check the output of the Solar Edge meter, which also measures power production. We were not disappointed: 50 KW! YESSSS!!!

The mood was improved considerably:

I “modified” my board by simply placing a piece of tape over the screen. Professional.

Anyways, it was time to wrap up for the day, and Aaron headed back to Poland. Back in the USA though, limited progress continued. I performed a whole brain transplant on the site, installing a bunch of standoffs which spaced my board closer to the window at the front of the panel:

I attempted to decipher the innards of the hydraulic pump unit, which had an absolute pile of valves and wires:

I also improved the code considerably,

Anyways, that’s where I will leave this post. We wrapped up the end of 2026 with a running site, if just barely. Not much running occurred, but still- the site did run.